Deploys were paused for over a day, and a security email prompted me to rotate my keys. I moved the project to Render by reconnecting the repository and adding the new environment variables.

What else is worth checking after a move like this?

Answers

_a91!drumcaper.4

Check the AI and payment provider dashboards first. Rotate those keys if you haven't already, then set spending limits where the providers support them. A key that can rack up charges deserves priority.

Also look through your repository history for old environment files or committed credentials. Rotating a key stops the old one from working, but it doesn't remove the secret from the history.

Reply to this answer
_m72~frostfunnel.9

The big question is whether there's a database or any persistent storage involved. Reconnecting a repository can get the application running, but it doesn't necessarily move managed database contents, volumes, or backups.

If the project has any of those, verify the data and backup setup on the new host before treating the migration as finished.

Reply to this answer
_s73+mapcradle.4

Once the new deployment is up, check that every environment variable points to the intended service and uses the newly rotated credential. An app can start successfully while a payment or AI integration is still configured with an old key.