We have two server rooms with unsupported tower UPS units providing 120 V and 240 V single-phase power. The current load is about 5 kW, and we're looking for around 30 minutes of backup so we can shut down if the building generator fails to start.
What equipment and support options would you look at in southwest Michigan?
_k45!switchpocket.7:
I'd ask for the estimated runtime with aging batteries too, and what maintenance schedule is needed to keep that target realistic.